RH Bophelo funded the design and implementation of an Energy Reduction Project for the Hillbrow Hospital were annual energy costs were projected to be US$1M.
Goals & Objectives
The primary objective was to develop and implement an Energy Reduction Project for the Hillbrow Hospital with a target electricity and carbon reduction goal of 45%. The Energy and Carbon Reduction Plan targeted the HVAC system by utilizing Ice Storage Air Conditioning.
Solutions
Service provided
Design of Efficient Chilled Water Pumping
Design of Efficient Gas Boiler
Design of an Energy Management System
Energy Management Software & IT Energy Modelling
Techno-Economic Modelling to establish the Business Case
Project Management
Measurement and Verification of Energy Saving
Results and Benefits
Financial Results
25% IRR
Capital Investment $1.75M
Annual Gross Savings $0.45M
2.5% COGS
Technologies applied
Efficient HVAC
VSD Pump Speed Control
Ventilation on Demand
Heat Pumps
Meter Technology
Online Electricity Dashboard
ESG Impact
750 tons CO2 savings

Project Location
Johannesburg, South Africa