Project
Challenges
Locate most reliable and competitive PV system supplier in remote area
Define optimum financial basis for Power Purchase Agreement (PPA)
Ensure system design and placement do not interfere with design of Resort
Goals & Objectives
Realize renewable energy supply at Resort at maximum achievable capacity
Full investment by renewable energy source operator against PPA
Solutions
Service provided
Conceptualization
Supplier selection
Financial structuring
Results and Benefits
Financial Results
Competitive power price fixed over 20-year term of PPA
100% of the investment upfront by system operator
Technologies applied
Power Generation (PV Solar)
ESG Impact
Approximately 400 kWp power supply by PV Solar System
Approximately 300 tons of CO2 offset

Project Location
Zannier Hotels Bãi San Hô, Hòa Thạnh, Xuân Cảnh, Song Cau, Phú Yên, Vietnam